Solution:
The pillar of USIBOR is made in 4 steps, 3
of them require a jig. The jigs are mounted
on a 2-station-rotating table. The welding
process employs 3 robots: 2 robots hold a
welding clamp and execute the welding
points with the pillar on the jig. The third
robot has a gripper and finishes the welding
with the free standing part by means of a
welding machine on the floor.
The unload is automatic: the third robot
deploys the finished part on the conveyor.
The load is made by an operator. |